Difference between Strip Footings & Pad Footings The Ultimate Guide To Start a Construction Company in 2022 You need to know about Stone Stairs How to Design a RCC Cantilever Beam? Road Estimator & Its Features Success of Your Project using Connected Construction Brief Note Calculate Weight of Steel 2400 sq ft RCC Roof Slab Retaining Wall Ideas to Quality for Brick Masonry Steps in Building a House Quality Tests on Stones and its types Green Buildings - The Future of Construction Create Templates in AutoCAD Some useful tips for reinforcement detailing Pitched Roof Design and Types Fineness test of Cement Surface Drainage Systems Executive Summary of Intelligent Compaction Bridge Abutment and Its Types Building Foundations and its types A Brief Note on Making a Manhole Uses of Roofs and Its Types Consider before your dream building Some Vital Guidelines to Erect a Bridge Cutting Length of Stirrups with different Shapes Maximum bearing capacity of various types of soil Types of Heavy Equipment used for Construction A Floor Column's Bar Bending Schedule Opens the World's Largest Canal Locks in Netherlands Unsung Hero of Fire Damage Restoration Services Heliports and Its Types What You Need to Know about Your Own Fence Bond Breaker Construction in Under 10 Minutes Hydrogen Power for the Construction Industry Pointing in Brick masonry and types Crack Repairs and Epoxy Injection Techniques Need to Know about Calacatta Marbles Made Simple MDF Wood and Its Types Plinth Beam and its Purpose A Brief Guide to Rebar Support and Chair How to Install a Toilet Properly Purpose & Construction of a Cavity Wall Design and analysis of Retaining Wall Different types of BBS shape codes for steel Differs between beam and lintel as per structural Top Tips for Crushing Your Vibration Risks in Construction Build a Solar Access Plan for your Building Site

A Floor Column's Bar Bending Schedule

A Floor Column's Bar Bending Schedule

Structural columns transfer loads from beams and slabs to the foundation and finally to the soil. A column bending schedule is simply a calculation of how much steel rod will be needed in order to maintain safety. In the neck column, the part of the column that lies deep inside the substructure is called the neck column.

Depending on the soil history, the type of construction, and the expected total load of the structure, the structural engineer determines the exact dimensions and shapes of the floor columns.

Calculation of Bar Bending Schedule in floor's Column

The construction steel is ordered either in kg or in the number of bars. A 12m-long bar is the standard size. Calculations for bending the bars of the column are divided into main reinforcement calculations and ties calculations. Longitudinal reinforcements are also known as ties, and main reinforcements are known as main bars.

Key Materials

  • Determine the length of each main bar.
  • Calculate the Main reinforcement length.
  • Determine how much steel is needed to reinforce 1 m of Main reinforcement.
  • Determine how much steel is needed for Main reinforcement.

Longitudinal Reinforcement

  • The formula tells you the length of the stirrup after subtracting the concrete cover from the ties on all sides.
  • By using the formula, determine how many ties are required.
  • Calculate the total amount of ties needed.
  • For every 1m of longitudinal reinforcement, calculate the weight of steel needed.
  • Calculate the total amount of steel that will be required for longitudinal reinforcement.

Some Important tips

Steel bars have a standard size of 12 meters. Then, if more height or length is needed, you can add additional rods. Make sure that you do not tie the steel rod at a place with a large bending moment. If the column has a top or bottom, avoid tie the steel rod there.

It's always better to lap the steel rod in the middle or near the middle of the column. A different way of lapping steel rods should use. There should be enough lapping to ensure safety as well as economics.

Important uses of hooks & bends

Standard dimensions are important for calculating hook lengths and bend lengths at corners during the process of estimating a floor column's bending schedule based on the cutting length.

  • One hook length equals nine diameters.
  • The length of a 45° bend equals one diameter.
  • The 90° bend length equals two diameters.
  • A 135° bend length equals three diameters.

Bar Bending Schedule of Floor's Column

  • Footing Thickness- 350mm.
  • Slab Thickness-125mm.
  • Floor Height-3000mm.
  • As an example, let's say that column has six bars of 20 mm in diameter.
  • A development length of 50d is 50x20 = 1000 mm.
  • Stirrups 8 millimeters thick at 150 millimeters center-to-center.
  • Clear Foot Cover = 40 mm.

Vertical Bar Length

A vertical bar's length equals its design length + clearance level + slab thicknesses (Sb) + overlap length - bend length.

Approximately equal to (50?20) + 350 + (2?3000) + (2?125) - (2?20) = 7560 mm or 7.560 meter.

In this case, Overlapping Length should not be considered since the standard size of steel rod is 12 meters. Using the equation above, the cutting length is equal to the total vertical bar length.

The overlapping length of the steel rod would be added if its length exceeded 12 meters. Having said that, let's calculate how long the steel rod of each column overlaps.

Lapping

It is understood that we need to take 50d = 50 * the diameter of the bar, or 50?20 = 1000 mm. The top and the bottom of a column should never overlap. Instead, alternate bars should be used. Bottom bars should always overlap top bars.

Cutting Length of Stirrups

  • The perimeter of Stirrup + Hooks + Bends = Stirrup Cutting Length
  • The perimeter of a column is equal to two times [the column width minus clear] plus [the column's length minus the clear cover].
  • Two times (500 - 25) plus (300 - 25) equals Perimeter. It has a length of 1500 mm.
  • The bend length is 3 x (2 x 20) + 2 x (3 x 20) = 240mm.
  • One hook has a length of 9d = 9 x 20 = 180 mm.
  • Consequently, the cutting length of a stirrup is equal to the perimeter of the stirrup plus the length of the hooks minus the length of the bends. In this equation, Length = 1500 mm plus 180 mm - 240 mm. So cutting length of stirrup is 1440mm.

Stirrup Number

Stirrups are needed if the length or spacing of vertical bars is longer than the number of stirrups plus one. There are 7760 stirrups needed, plus one extra stirrup for good measure equals to 51.4 Stirrups or 52.